III |
NOS
REFERENCES |
 |
GUINEE-BISSAU |
REFERENCES TECHNIQUES
|
PROJET
|
CLIENT |
FINANCEMENT |
MONTANT DU
CONTRAT EN FRANCS C.F.A |
ANNEE DE DEMARRAGE
DES TRAVAUX |
DELAI D'EXECUTION |
DATE D'ACHEVEMENT |
Construction
d'un Immeuble R + 2 à Bissau
( Logements Coopérative ) |
F.A.C |
F.A.C(
PARIS ) |
150,000,000 |
01
/06 / 1980 |
12
Mois |
1981 |
| Réhabilitation
Bureaux (
250 m2 ) |
F.A.C |
F.A.C(
PARIS ) |
111,500,000 |
01
/11 / 1980 |
12
Mois |
1981 |
| Construction
de hangar de stockage |
USAID |
USAID
( BISSAU ) |
154,400,000 |
01
/ 09 / 1983 |
5
Mois |
1983 |
| Construction
du Centre de Formation CENFA |
M.E.N.C. |
B.A.D. |
1,523,370,850 |
01
/ 10 / 1992 |
13
Mois |
1994 |
| Pistes
OIO - BAFATA |
M.C.I.
BISAUU |
FED |
1,270,000,000 |
15/07/1996 |
13
Mois |
15/09/1997 |
| Ponts
à Binar - Bissora |
FED |
FED
/ Direction Routes & Ponts& Equipement
Social |
454,956,382 |
Mai
1998 |
14
mois |
2000 |
|
|
|
|
|
|
|
REFERENCES TECHNIQUES ( ROUTES - V.R.D
ET TERRASSEMENT )
PROJET |
CLIENT |
FINANCEMENT |
MONTANT
DU CONTRAT EN FRANCS C.F.A |
ANNEE
DE DEMARRAGE DES TRAVAUX |
DELAI
D'EXECUTION |
DATE
D'ACHEVEMENT |
| VRD
CENFA ( 1 km) |
M.E.N. |
sodetec |
170,000,000 |
1994 |
3
mois |
1995 |
| Piste
Rio Calium ( 20 km) |
MARPLES |
ITI |
700,000,000 |
1994 |
9 MOIS |
1995 |
| Ouvrages d'art
pour les 110 km de piste Région de Bafata |
MARPLES |
ITI |
430,000,000 |
1994 |
|
|
Réhabilitation
de 116 kms de piste dans la région de
Oio - Bafata (
90 km de piste et 26 km de route bitumée
) |
Ministère
Plan et
Coopération Internationale |
T.P
Bissau |
2,066,949,219 |
Juillet
1996 |
12
mois |
Fin
Juillet 1997 |
|
|
|
|
|
|
|
|